WILLIAM RANSOM PRIMARY SCHOOL, HITCHIN

Client
Willmott Dixon

Contract value

£198,000

Description of works
A single storey tall extension to the school hall and an extensive list of internal refurbishment with a tight programme to be ready for the new school year.

The extension was a steel frame with Metsec infill panels, clad with Trespa. The roof was covered with Resitrix single ply membrane and parapets with aluminium capping and rainwater goods.

Internally, the existing schoolrequired refurbishment including new flooring, demountable ceilings, new WC's with IPS panels and complete redecoration of the corridor areas.

We also built a small retaining wall adjacent to the extension and formed a lift shaft.

IMG_2347
IMG_2227
IMG_2160
IMG_2161
IMG_2166
IMG_2215
IMG_2210
IMG_2212
IMG_2218
Cut & carve
Cut and carve
Demo soft strip, making good
Main contracting
Main contracting
Multi trade subcontracting
Multi trade
Passive fire protection
Fire collar
Secondary steel
Welfare & site setup
Welfare & site setup
About us
About us
Contact us
Contact us
Accreditations
Accreditations
Show More

110 High Road

Loughton

IG10 4HJ

Tel: 0208 508 6060

© 2017-2020 Mossford Construction Co Ltd